Hancock County Engineering Garage Nearing Completion


7/22/14 – 12:19 P.M.
What looks to be the final change order for the new Hancock County engineering garage has been submitted to the county commissioners. If approved, what was submitted as a little more than a $2.6 million project will finish up at a little more than $2.8 million.
Commissioner Brian Roberston says that’s pretty good all things considered…
Audio: Brian Robertson
The latest change includes more than $45,000 to install a natural gas pump.
Robertson says they had to have a special pump installed…
Audio: Brian Robertson
The gas pump will help the generator for the facility fire in case of a power outage.
Today’s change order was for $75,740. The total for all change orders to the project was a little more than $128,000.
The final change order was tabled by the commissioners today for review.